The entire construction was secured to the 30-metre high ceiling with 45 specially designed suspension points and linked with custom-made corner sections and connectors. The lift that took Guus Meeuwis (artist) safely to a height of 15 metres was also designed specifically for the show. Meeuwis was therefore the first artist to look directly into the eyes of the fans in the dress circle.
The process
-
1 From demand to solution
The requirement was as clear as it was enormous. The solution was obvious but would we be able to realise it in close collaboration with the producers of Amstel Live? They were familiar with the location and we had our specialist knowledge so together, we came up with a customised design. Design, engineering and execution were the next steps.
-
2 Drawing and calculating
In collaboration with producers and the architects for the location, the engineers of Altrex set to work on designing a construction and guaranteeing stability. A precise construction plan and a strength and stability calculation guaranteed the structure. The customised system thus fulfilled all of the necessary legislation and regulations.
-
3 Safety and certainty
A specific and vital requirement was, of course, the guaranteed stability of the construction. Guus (artist) was able to move freely, jump around and even dance on the suspended platforms. The artist, audience and organiser were able to rely on the safety of the construction. A reassuring notion, particularly for those under the suspended platforms.

Dress circle, top-class
The production company for Vrienden van Amstel Live can look back on a memorable event. The access solution was an eye-catching addition to the overall show and particularly in terms of the experience of those in the dress circle, who actually ended up with 'first-row seats' for some of the show on all seven evenings.
Collaboration and good preparation led to a spectacular and safe solution. For both the artist and the visitors. The suspended platform construction was built quickly and easily by the Altrex builders. It was exceptional in every respect."
Real custom work starts with contacting the Altrex specialist
Are you also facing a challenge? Our engineers will be pleased to help you on your way to the best solution.